The New Service Process Guide

Six Predictable Phases from Start to Meter Set

Our mission is to help you with your new service connection and to ensure you achieve your project goals. Establishing new service with us is a six-phase process. Use this guide to learn what you need to do during the process and what we'll be doing along the way.

1

Initiation

Typically 2-4 weeks*

2

Design

Typically 6-8 weeks*

3

Inspection

Typically 24-48 hours*

4

Scheduling

Typically 2-4 weeks*

5

Construction

Typically 4-6 weeks*

6

Meter Set

Typically 72 hours*

*Note: timeframes may vary depending on project complexity, the timeframes provided are averages for you to use as a guideline for planning purposes only